The maintenance standby time of cement mill
Release Date: 2011.10.31 Views:

    The cement mill bearing on the processing of the base is in the same cement mill horizontal surface, the center spacing tolerances 1 mm, not parallel longitudinal centerline of deviation 0.5 mm, and cement mill horizontal deviation of the centerline of 0.5 mm per metre .

    cement mill Watts Block spherical contact angle should to be uniform for each 50 ⅹnot less than 50 mm2, 1-2; hollow shaft contacting with the Vanuatu should be 90 -100 every square inch should be no less than 2:00, the cement mill Journal and bearing clearance on both sides should approximate the same.cement mill with the cement mill front flange cylinder cover should ensure that the cement mill co-ordination of good cement mill contacts, and no pads, two different hollow shaft axis of less than 0.8 mm tolerance, when the cement mill ring gear in connection with the cylinder assembly correction,the thrust should be solid,cement mill liner should be installed to their installed Cover, cylinder liner from the cement mill population, beginning with the assembly requirements, the screws tight to the uniform, not leaking. There should be no rubber liner with crack, and crevice use the sponge blocked.

 

   

Specification Output
t/h)
Rev (r/min) Grinding Body
(t)
Electricmotor Reducer
Model Power
(kw)
Model Ratio of Speed
φ1.83×7 material22 24.5 20 JR138-8 245 ZD60-9 4.5
φ2.2×75 material22 21.4 31 JR158-8 380 ZD70-9 5
φ2.2×11 material22-26 21.4 49 JR1512-8 630 ZDH80-4 4.5
φ2.2×12 material26-30 21 58 YR630-8 630 JS-90 35.2
φ2.4×7.5 material21-23 20.4 28 JR158-8 380 NZD450-5 5

    We also offer a more cost effective cement mill line called the series cement mill.f you have any interesting with our cement mill products, please telephone us: 0086-0371-55902866 or leave us a message: info@zkcorp.com.
 

Contact Us